Recently received from Michael Krempel (WSSC), reflecting the end dates and the various stages of the WSSC project.  

Please see the updated MAP HERE

Phase 1 is complete – Kensington Prkwy and part of Calvend

Phase 2- currently working on

Phases 3-5 – to come

Projected end date for entire project is February 26, 2021.