We’ve received an update on WSSC’s water main replacement project for our neighborhood.

• Notice to proceed was Sept 10, 2018
• The contractor has 900 days to complete this project (Must be done by Feb 26th, 2021)
• The work will probably start any day, as the stakeout has been completed and information signs have been posted

The work will be staged; please see the map at:
https://rchca.org/wp-content/uploads/2018/11/Revised-Phase-Sequence-Proposal-Kensington-Rock-Creek.pdf

For some background, notes summarizing a July 2016 informational meeting regarding this project may be found at https://rchca.org/2016/07/25/1596/